The Challenge: A renovation at this scale means new electrical infrastructure tied into a system that is already in place and running. Existing equipment, existing service conditions, and new distribution all had to be modeled and evaluated as one system. On top of that, Eleculator was engaged while design changes were still in progress, so the study had to track a system that was still changing underneath it.
Our Solution: We performed a full short-circuit, protective device coordination, and arc-flash study covering approximately 300 pieces of electrical equipment. The design documents had gaps, as they do at that stage. Rather than wait, we relied on our electrical design background to fill them with sound engineering assumptions and move the study forward to preliminary results, then fine-tuned the study as information was validated. Document and data control were as much a part of the scope as the analysis. We maintained strict version control so every design change was incorporated accurately as it came, and the final study reflected the system as built rather than an earlier snapshot of it.
The Results: We identified deficiencies in the proposed equipment ratings and device selection that required corrective action before equipment could be released. Because they surfaced during the study phase rather than at startup, the corrections were made on the shop floor prior to delivery. No field modifications were required.